Question: 4. The table below shows the activities, duration, and precedence relationships required to complete a project for Berjaya Enterprise. Predecessors Duration (week) 3 4 A

4. The table below shows the activities,

4. The table below shows the activities,

4. The table below shows the activities,

4. The table below shows the activities, duration, and precedence relationships required to complete a project for Berjaya Enterprise. Predecessors Duration (week) 3 4 A Activity A B C D E F G H 7 2 1 B, C, D B. F E 5 6 2 Determine the Earliest Event Time (Tail) for activity E. A. 2 weeks B. 7 weeks C. 10 weeks D. 12 weeks d2 E,1 H,3 3 6 A,4 7 1,4 D, 1 8 B,2 0,7 F,3 G2 N 4 5 d1 Based on the above PERT diagram, determine the project completion time. A 8 weeks B. 10 weeks C. 12 weeks D. 14 weeks 6. 1 4 6 7 Node EET LET 0 0 ONN 5 10 0000 14 14 22 22 13 The above table shows the EET and LET for all events in a project. Identify the critical path for the project. 13. A time study was performed on a fish aquarium assembly operation covering an 8-hour shift. The allowances given to the workers are 2.5% rest period and one contingency hour per day. Compute the total allowance factor. A 5% B. 10% C. 12% D. 15% 14. Based on the information given, calculate the normal time of the entire operation. Element Observed time in minutes Performance Rating (%) 110 1 4 5 3 2 12 15 18 90 3 I 7 20 9 100 A. 17.87 minutes B. 21.5 minutes C 25.9 minutes D 28.6 minutes 15. Given the total normal time of an operation is 46,7 minutes with a 10% allowance factor Determine the standard time per output A. 42.03 minutes B 46.70 minutes C 51.37 minutes D. 51 90 minutes 16 Assuming a worker works an 8-hour shift 26 days per month. Calculate the monthly production units with a standard time of 80 minutes A 156 units

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!