Question: 4. Using A-O-N, diagram the network described below for Samantha's construction project. a) Calculate its critical path. b) How long is the minimum duration of

4. Using A-O-N, diagram the network described
4. Using A-O-N, diagram the network described below for Samantha's construction project. a) Calculate its critical path. b) How long is the minimum duration of this network? Activity Predecessor Time (weeks) J 10 8 K J L M J K K L M, N, O 6 3 2 7 N O Answer: a) Critical Path (weeks) b) Minimum duration of this network (weeks) Show you're A-O-N diagram here