Question: Using AOA, diagram the network described below for Lillian Fok's construction project. Calculate its critical path. How long is the minimum duration of this network?
Using AOA, diagram the network described below for Lillian Fok's construction project. Calculate its critical path. How long is the minimum duration of this network?
Step by Step Solution
3.45 Rating (152 Votes )
There are 3 Steps involved in it
Here is the activityonarrow AOA diagram for the network J 10 12 K 8 13 L 6 24 M 3 23 N 2 34 O ... View full answer