Question: 4. Using A-O-N, diagram the network described below for Samantha's construction project. a) Calculate its critical path. b How long is the minimum duration of

 4. Using A-O-N, diagram the network described below for Samantha's construction

4. Using A-O-N, diagram the network described below for Samantha's construction project. a) Calculate its critical path. b How long is the minimum duration of this network? Activity Predecessor Time (weeks) YJZZOQ M. N. O Answer: Critical Path (weeks) Minimum duration of this network (weeks) Show you're A-O-N diagram here

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!