Question: 40 40 A E 25 20 30 F G 35 25 B D All times are in seconds in the precedence diagram. In this precedence

40 40 A E 25 20 30 F G 35 25 B D All times are in
40 40 A E 25 20 30 F G 35 25 B D All times are in seconds in the precedence diagram. In this precedence diagram the total task time is 215 sec. Cycle time is 75 sec/unit Workstation #1 is AB Four of the following workstations are NOT valid. Based on the information provided, which one of the following workstations would be a valid workstation #2? O EF O CDF O CF O CE O DF