Question: 40. A project has three paths and a desired completion time of 43 days. The first path has a 70 percent probability of being completed

40. A project has three paths and a desired
40. A project has three paths and a desired completion time of 43 days. The first path has a 70 percent probability of being completed in 43 days. The second has an 85 percent probability and the third haws a 90 percent probability. What is the probability that the project will be completed on time? a) 53.55 percent b) 70 percent c) 90 percent d) 99.55 percent