Question: (40 pt) 6. You need to do a PDM schedule for the following project. Include Critical path, total float and free float Activity Section Predecessor||Activity

(40 pt) 6. You need to do a PDM schedule for the

(40 pt) 6. You need to do a PDM schedule for the following project. Include Critical path, total float and free float Activity Section Predecessor||Activity JA IJ B D Total Duration Duration 15 3 START 20 4 START 25 5 START 20 4 A 35 7 A,B 15 3 B,C 25 5 C 20 4 DE 10 2 DE JK JL M Total Section Predecessor Duration Duration 15 3 F 25 5 F,G 20 4 H 30 6 I.J 35 7 J 15 3 K 25 5 L.M N,O,P JE N F 10 IP G END

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!