Question: . Draw a PDM for the schedule below. Include total float, free float, and critical path. Each activity is based on the project having 5
. Draw a PDM for the schedule below. Include total float, free float, and critical path. Each activity is based on the project having 5 sections.
Please Include FF and SS for each activity (Finish to Finish, Start to Start)
Duration / 5 = time for each section
| Activity | Duration | Predecessor | Activity | Duration | Predecessor | |
| A | 10 | START | I | 45 | F,G | |
| B | 20 | START | J | 30 | G,H | |
| C | 35 | A | K | 15 | F | |
| D | 15 | A,B | L | 35 | J,K | |
| E | 25 | B | M | 10 | J | |
| F | 15 | C | N | 15 | I,J | |
| G | 25 | C,D | O | 25 | L,M | |
| H | 15 | D,E | END | N,O |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
