Question: . Draw a PDM for the schedule below. Include total float, free float, and critical path. Each activity is based on the project having 5

. Draw a PDM for the schedule below. Include total float, free float, and critical path. Each activity is based on the project having 5 sections.

Please Include FF and SS for each activity (Finish to Finish, Start to Start)

Duration / 5 = time for each section

Activity

Duration

Predecessor

Activity

Duration

Predecessor

A

10

START

I

45

F,G

B

20

START

J

30

G,H

C

35

A

K

15

F

D

15

A,B

L

35

J,K

E

25

B

M

10

J

F

15

C

N

15

I,J

G

25

C,D

O

25

L,M

H

15

D,E

END

N,O

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!