Question: Draw a PDM (Precedence Diagram Method) for the schedule below. Include total float, free float, and critical path. Each activity is based on the project

Draw a PDM (Precedence Diagram Method) for the schedule below. Include total float, free float, and critical path.

Each activity is based on the project having 5 sections.

Activity

Duration

Predecessor

Activity

Duration

Predecessor

a

20

START

i

90

f,g

b

40

START

j

60

g,h

c

70

a

k

30

f

d

30

a,b

l

70

j,k

e

50

b

m

20

j

f

30

c

n

30

i, j

g

50

c,d

o

50

l,m

h

30

d,e

END

n, o

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!