Question: Draw a PDM (Precedence Diagram Method) for the schedule below. Include total float, free float, and critical path. Each activity is based on the project
Draw a PDM (Precedence Diagram Method) for the schedule below. Include total float, free float, and critical path.
Each activity is based on the project having 5 sections.
| Activity | Duration | Predecessor | Activity | Duration | Predecessor | |
| a | 20 | START | i | 90 | f,g | |
| b | 40 | START | j | 60 | g,h | |
| c | 70 | a | k | 30 | f | |
| d | 30 | a,b | l | 70 | j,k | |
| e | 50 | b | m | 20 | j | |
| f | 30 | c | n | 30 | i, j | |
| g | 50 | c,d | o | 50 | l,m | |
| h | 30 | d,e | END | n, o |