Question: 44. The front schedule logic causes all the work to be done ahead of schedule which: I. creates additional inventory II. saves expense III. intended

44. The front schedule logic causes all the work

44. The front schedule logic causes all the work to be done ahead of schedule which: I. creates additional inventory II. saves expense III. intended to allow workers to go home earlier IV. occupies resources that could be used on other orders O IV and Il only II and Ill only I and II only I and IV only III and IV only