Question: Based on the following table, calculate the ES, EF, LS, LF and Slack for each activity using an expected completion time of 16 weeks. Please

  1. Based on the following table, calculate the ES, EF, LS, LF and Slack for each activity using an expected completion time of 16 weeks. Please use the table format presented in the text to solve this problem. Please create one table with the original plan and a second table with the updates based on actual performance.

What is the critical path for the original project? If the critical path changes as a result of actual progress, identify the new critical path.

Can the project be completed on time? If necessary, identify activities you would focus on to get the project back on schedule.

Activity

Estimated Duration

Actual Finish Time

Immediate Predecessor(s)

A

3

2

-

B

3

5

-

C

4

8

A

D

9

A,B

E

4

B

F

5

C,D,E

What is the critical path for the original project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!