Question: 461 In project scheduling terminology, what do we call activities that must be completed before other activities can begin? out of Select one O a

461 In project scheduling terminology, what do we
461 In project scheduling terminology, what do we call activities that must be completed before other activities can begin? out of Select one O a schematics b. critical activities C. immediate predecessors d. temporal priorities