Question: 5 1 point What differentiates Material Requirements Planning ( MRP ) from Distribution Requirements Planning ( DRP ) in supply chain management? MRP is concerned
point
What differentiates Material Requirements Planning MRP from Distribution Requirements Planning DRP in supply chain management?
MRP is concerned with the requirements for production, while DRP deals with finished goods inventory allocation.
DRP is used exclusively for shortterm planning, whereas MRP is used for longterm strategic decisions.
MRP focuses on the demand from end customers, while DRP focuses on internal production requirements.
MRP and DRP both primarily focus on optimizing transportation costs within the supply chain.