Question: 5. (10 points) A project has seven activities: A, B, C, D, E, F, and G. Activities A, B can start anytime. Activity A must

5. (10 points) A project has seven activities: A,

5. (10 points) A project has seven activities: A, B, C, D, E, F, and G. Activities A, B can start anytime. Activity A must be completed before activity C and D can start. Activities E and F can start as soon as Activity B and C are completed. Activities D and E must be completed before Activity G can start. Activity G and F must be completed before ending the project. Optimistic time estimate for activities are as followings: A = 1, B = 2, C = 2, D = 3, E = 4, F = 0 and G =2. Pessimistic time estimate for activities are as followings: A = 7, B = 2, C = 8, D = 5, E = 8, F = 6 and G = 8. . Most likely time estimate for activities are as followings: A = 4, B = 2, C = 5, D = 4, E = 6, F = 0 and G = 5. All units are days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!