Question: A project comprises of activities A, B, C, D, E, F. The duration of project is 210 days. The duration for activity D is 61
A project comprises of activities A, B, C, D, E, F. The duration of project is 210 days. The duration for activity D is 61 days and it has the slack of 11 days. Suppose activity D is delayed and no other activity is delayed. As a result of this delay in D, the project duration increased by 50 days. What is the delay (in number of days) in activity D