Question: 5. A project with Earned Value (EV)=$250, Actual Cost (AC)=$200 and Planned Value ( PV )=$350. What is the Schedule Performance Index (SPI)? a. 1.25

5. A project with Earned Value (EV)=$250, Actual
5. A project with Earned Value (EV)=$250, Actual Cost (AC)=$200 and Planned Value ( PV )=$350. What is the Schedule Performance Index (SPI)? a. 1.25 b. 0.80 c. 0.71 d. 1.40 6. A project with Earned Value (EV)=$250, Actual Cost (AC)=$200 and Planned Value ( PV )=$350. What is the Cost Performance Index (CPI)? a. 1.25 b. 0.80 c. 0.71 d. 1.40