Question: If earned value (EV) = 450, actual cost (AC) = 500, and planned value (PV) = 425, what is schedule performance index (SPI)? Question 6

If earned value (EV) = 450, actual cost (AC) = 500, and planned value (PV) = 425, what is schedule performance index (SPI)? Question 6 options: 0.9 0.94 1.05 1.11