Question: 5 Calculation questions, 10 points each 1. A specific product has demand during lead time of 350 units, with a standard deviation during lead time

5 Calculation questions, 10 points each 1. A

5 Calculation questions, 10 points each 1. A specific product has demand during lead time of 350 units, with a standard deviation during lead time of 80 units. Management wants a 99% service level. a) What value of Z should be applied? b) How many units should be carried as safety stock? c) What is the appropriate reorder point