Question: 5. Describe the critical path and critical node in project management. Find out the critical path for the following table. Also find out Early
5. Describe the critical path and critical node in project management. Find out the critical path for the following table. Also find out Early Start, Early Finish, Late Start, Late Finish of all the nodes using CPM. [CO3] Node A B C D E F G H Duration (week) Precedence 2 5 3 4 4 6 4 3 A A B B, C D, E E G, F 8