Question: 5) Earned Value Management 2 (30 points) A project is defined by the network precedence diagram given below. At the end of day 7, the

5) Earned Value Management 2 (30 points) A

5) Earned Value Management 2 (30 points) A project is defined by the network precedence diagram given below. At the end of day 7, the Project Manager provided an update regarding the percentage of the individual tasks that had been completed as well as the actual costs incurred on the project. Predecessor Activity Duration (Days) 1 Actual Cost ($) 110 20 40 90 B 2 A A %Complete 100 100 40 80 6 C D ODD B 3 Budget ($) 90 40 90 60 100 40 55 70 40 100 E C 4 PUNwON F 2 5 7 G F Decrease Font Size 40 30 60 100 50 100 1 I J D, E, G H 5 Based on this information, calculate: a) The cost variance b) The schedule variance c) The cost performance index d) The schedule performance index Show the work that was used to calculate these values. 5) Earned Value Management 2 (30 points) A project is defined by the network precedence diagram given below. At the end of day 7, the Project Manager provided an update regarding the percentage of the individual tasks that had been completed as well as the actual costs incurred on the project. Predecessor Activity Duration (Days) 1 Actual Cost ($) 110 20 40 90 B 2 A A %Complete 100 100 40 80 6 C D ODD B 3 Budget ($) 90 40 90 60 100 40 55 70 40 100 E C 4 PUNwON F 2 5 7 G F Decrease Font Size 40 30 60 100 50 100 1 I J D, E, G H 5 Based on this information, calculate: a) The cost variance b) The schedule variance c) The cost performance index d) The schedule performance index Show the work that was used to calculate these values

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!