Question: 5. Given a directed, connected and weighted graph which represents an AOE network. (a) What is the critical path in this network? (3%) (b) Compute
5. Given a directed, connected and weighted graph which represents an AOE network. (a) What is the critical path in this network? (3%) (b) Compute the earliest time and the latest time of each activity. (4%) (c) Assume the unit of each edge in the graph is second. Is it possible to finish the plan in 25 seconds? Why? (3%) T 46-6 2,-6 Z 2105 24-4 ar 7 Q2=8 X Start s E End W as 3 265 Q11-3 ag=5 Y