Question: 5. Given a directed, connected and weighted graph which represents an AOE network. (a) What is the critical path in this network? (3%) (b)
5. Given a directed, connected and weighted graph which represents an AOE network. (a) What is the critical path in this network? (3%) (b) Compute the earliest time and the latest time of each activity. (4%) (c) Assume the unit of each edge in the graph is second. Is it possible to finish the plan in 25 seconds? Why? (3%) T 96-6 a-6 a-4 Z a7-7 105 Start S a2-8 X E End as 3 agh 5 Wa11-3 ag-5 Y a-4