Question: 5. Given this dataset for jobs that need two processes in sequence, please answer the following questions Job Processing Time A Processing Time B 1

5. Given this dataset for jobs that need two processes in sequence, please answer the following questions

Job

Processing Time A

Processing Time B

1

4

8

2

2

6

3

7

8

4

7

3

5

5

6

6

9

4

7

2

2

8

6

2

a) How many different schedulings does a problem of this size have?

b) How many schedulings of a problem of this size (at most) could minimize makespan?

c) Please compute a makespan-minimizing schedule for this problem.