Question: 5. Jane was constructing a PERT for activities on a rehabilitation project. She listed activities A through F. Activity Ds immediate predecessors are Activities E
5. Jane was constructing a PERT for activities on a rehabilitation project. She listed activities A through F. Activity Ds immediate predecessors are Activities E and F. E and F were the finished activities. E and Fs earliest finish time was E-22 and F-18. What will be the latest finish time for activity D.? A. 18 B. 16 C. 4 D. 22