Question: 5) On the Forward Pass through the network diagram: A) Calculate the Late Start and Late Finish for each activity and use the higher number

5) On the Forward Pass through the network diagram: A) Calculate the Late Start and Late Finish for each activity and use the higher number at the points of convergence B) Calculate the Late Start and Late Finish for each activity and use the lower number at the points of convergence C) Calculate the Early Start and Early Finish for each activity and use the lower number at the points of convergence D) Calculate the Early Start and Early Finish for each activity and use the higher number at the points of convergence 6) The Scope Baseline for the project consists of: A) The Project Charter, the Scope Management Plan, and the WBS B) The approved version of the Project Scope Statement, the WBS, and the WBS dictionary C) The Requirements Documentation, the WBS, and the Activity List D) The Requirements Documentation, the WBS dictionary, and the work packages Three point estimating: A) Estimates the duration for scope, cost, and schedule B) Uses optimistic, most likely and pessimistic estimated durations to calculate expected duration C) Estimates the duration, carly start and early finish for an activity D) Estimates the start date, end date, and the total critical path for the project
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts