Question: 51. The optimistic time for completion of Activity X on a PERT chart was 6 hours, the most likely time was for this

51. The optimistic time for completion of
51. The optimistic time for completion of Activity " X " on a PERT chart was 6 hours, the most likely time was for this same activity was 9 hours and the pessimistic time was 12 hours. Using the Beta distribution formula, what is the mean time expected for Activity X? The mean time cannot be calculated with this information 9 hours is hours 10 hours Question 52 0/2 pts 52. Using the information in Problem #51, calculate the variance of Activity X. The variance cannot be calculated with this informution 1.0 20 160