Question: An activity on a PERT network has an optimistic time of 4 hours, a most likely time of 5 hours, and a pessimistic time of

An activity on a PERT network has an optimistic
An activity on a PERT network has an optimistic time of 4 hours, a most likely time of 5 hours, and a pessimistic time of 31 hours. Find its EXPECTED TIME. 40 hours 6.66667 hours 44 hours 9.16667 hours 55 hours

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!