Question: 6 and 7 Question 6 (2 points) In precedence network analysis, knowing the slack time allows managers to: OA) delay critical activities. B) increase the

6 and 7
Question 6 (2 points) In precedence network analysis, knowing the slack time allows managers to: OA) delay critical activities. B) increase the critical path. OC) decrease the project duration. OD) extent the project if necessary. OD) pay attention to activi illigs that could delay the project. Question 7 (2 points) In "crashing a project manager will generally focus on activities which: A) are the least costly to crash. B) are costly to crash and are on the critical path. C) are not on the critical path. D) have the most slack D) are on the critical bath anStep by Step Solution