Question: In precedence network analysis, knowing the slack time allows managers to: a . pay attention to activities that could delay the project b . delay
In precedence network analysis, knowing the slack time allows managers to:
a pay attention to activities that could delay the project
b delay critical activities
c decrease the project deadline
d increase the critical path
e extend the project if necessary