Question: 6. Given the following data, calculate the projected available, available to promise and the planned MPS receipts. The demand time fence is 3 weeks and

6. Given the following data, calculate the
6. Given the following data, calculate the projected available, available to promise and the planned MPS receipts. The demand time fence is 3 weeks and the order quantity is 200. Week 1 2 3 4 5 6 Forecast 150 140 130 120 110 100 Customer Orders 110 80 170 130 70 90 Projected Available 120 MPS Receipts Available to Promise