Question: . Given the following data, calculate the projected available, available to promise and the planned MPS receipts and the order quantity is 120. The customer
. Given the following data, calculate the projected available, available to promise and the planned MPS receipts and the order quantity is 120. The customer has been finalized her order for the first two weeks.
| Week |
| 1 | 2 | 3 | 4 | 5 | 6 |
| Forecasted Demand |
| 140 | 130 | 120 | 110 | 100 | 90 |
| Customer Orders |
| 120 | 110 | 90 | 100 | 120 | 100 |
| MPS Receipts | 120 |
|
|
|
|
|
|
| Available to Promise |
|
|
|
|
|
|
|
| Adjustment (In case) |
|
|
|
|
|
|
|
Step by Step Solution