Question: #6 In the latest earned value report for your project, the CPI is 1.1, the SPI is 0.8, the PV is 559514 , and the

#6
#6 In the latest earned value report for your
In the latest earned value report for your project, the CPI is 1.1, the SPI is 0.8, the PV is 559514 , and the SV is $111902.8. Calculate the CV based on the information given. none of the given answers 488303 264498 40692 742628 Skip this question to avoid any negative scorel