Question: Q1- In the latest earned value report for your project, you see the CPI is 1.2, the SPI is 0.8, the PV is $600,000, and

Q1- In the latest earned value report for your project, you see the CPI is 1.2, the SPI is 0.8, the PV is $600,000, and the SV is -$120,000. You can't find the CV in the report, so you need to calculate it based on the information given. What is the CV? Q2- What is the SPI if the CV is $10,000, the SV is -$3,000, and the PV is $100,000? Q3- What is the EV if your CPI is 1.1, your SPI is .92, and your AC is $10,000? Q4- Use this earned schedule table to determine the schedule variance ($) for this project at the end of Month 6. Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 PV ($) $125 $275 $500 $875 $1,485 $2,325 $2,670 EV ($) $50 $120 $255 $420 $715 $865 $0
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
