Question: 6) Screen a. Full Page Apply the Task Duration formula (Task Duration = Work / Resource Availability) for any of the tasks listed in your


6) Screen a. Full Page Apply the Task Duration formula (Task Duration = Work / Resource Availability) for any of the tasks listed in your course project. . You want to use the Task Duration formula to estimate durations of all the tasks in your course project. . Write a report illustrating the application of the formula for any four of those tasks. Use the following formula (Example 1: If Work = 4 days, and Resource Availability = 2 people, then Task Duration = 4 days / 2 people = 2 days.): i. Task Name:? ii. Work =? (Explain how you determined this value for this task) Resource Availability =? (Explain how you determined this value for this task) iv. Task Duration =