Question: begin { tabular } { | l | l | } hline An activity has an early start ( ES ) of day

\begin{tabular}{|l|l|}\hline An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day \\9, and a late finish (LF) of day 19. The activity: \\\hline A) Is on the critical path. & B)\\\hline C) Is progressing well. & D) Is a lag. \\\hline \end{tabular}\begin{tabular}{|l|l|}\hline \multicolumn{3}{|l|}{ AO activity diagrams are only represented using which representation? }\\\hline A) Start-to-Start & B)