Question: 7. Estimate at completion (EAC) is calculated how? a. BAC / CPI - Used if no variances from the BAC have occurred b. AC +
7. Estimate at completion (EAC) is calculated how?
a. BAC / CPI - Used if no variances from the BAC have occurred
b. AC + ETC - Actual plus a new estimate for remaining work. Used when original estimate was fundamentally flawed
c. AC + BAC EV - Actual to date plus remaining budget. Used when current variances are atypical.
d. AC + (BAC EV) / CPI - Actual to date plus remaining budget modified by performance. When current variances are typical.
e. All of the above