Question: 7. Given an activity in an advertising project whose planned cost was $12,000 but actual cost to date is $10,000 so far and the value
7. Given an activity in an advertising project whose planned cost was $12,000 but actual cost to date is $10,000 so far and the value completed is only 70 percent, calculate the cost and schedule variances. Will the client be pleased or angry