Question: Problem: Given an activity in an advertising project whose planned cost was $20,000 but actual cost to date is $22,000 so far and the value

Problem: Given an activity in an advertising
Problem: Given an activity in an advertising project whose planned cost was $20,000 but actual cost to date is $22,000 so far and the value completed is only 80 percent, calculate the cost and schedule variances and cost and schedule indexes. Will the client be pleased or angry