Question: Given an activity in an advertising project whose planned cost was $12,000 but actual cost to date is $10,000 so far and the value completed

Given an activity in an advertising project whose planned cost was $12,000 but actual cost to date is $10,000 so far and the value completed is only 70 percent, calculate the cost and schedule variances. Will the client be pleased or angry?

Step by Step Solution

3.40 Rating (175 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

000 AC PV EV 100 120 84 CV 16 Unfavorable CPI 084 SV ... View full answer