Question: 7 Given the following data for the tasks in a production process what is the total completion time of the project? table [ [

7 Given the following data for the tasks in a production process what is the total completion time of the project?
\table[[\table[[Task],[name]],\table[[Duration],[(days)]],\table[[Immediate],[Predecessor]]],[A,5,],[B,2,A]]
C
3
A, B
D 3
A
E 4
D
F
2
C, E
Your answer
12
14
16
11
 7 Given the following data for the tasks in a production