Question: 7. You are the Project manager for a project where the Schedule Performance Index (SPI) is 0.85 and Cost Performance Index (CPI) of 0.90. The
7. You are the Project manager for a project where the Schedule Performance Index (SPI) is 0.85 and Cost Performance Index (CPI) of 0.90. The project is currently:
ahead of schedule and over budget
behind schedule and under budget
ahead of schedule and under budget
behind schedule and over budget
8 What is the Schedule Variance (SV) for a project where
Earned Value (EV) = $8000,
Actual Cost (AC) = $6000 and
Planned Value (PV) = $6000.
Group of answer choices
-2000
0
2000
-1000
10. Earned value credit for labor is taken when the labor is hired.
True
False
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
