Question: A project with both Schedule Performance Index (SPI) and Cost Performance Index (CPI) of 0.40 The project is currently: Question 48 options: behind schedule and
A project with both Schedule Performance Index (SPI) and Cost Performance Index (CPI) of 0.40 The project is currently: Question 48 options: behind schedule and over budget behind schedule and under budget ahead of schedule and under budget ahead of schedule and over budget