Question: A project with both Schedule Performance Index ( SPI ) and Cost Performance Index ( CPI ) of 1 . 2 0 . The project
A project with both Schedule Performance Index SPI and Cost Performance Index CPI of The project is currently:
behind schedule and under budget
ahead of schedule and over budget
behind schedule and over budget
ahead of schedule and under budget