Question: Project Time Management Strategies Q1. From the table information below i) Draw the network diagram (Points 5) Show ALL the network paths (Points 2) iii)

Q1. From the table information below i) Draw the network diagram (Points 5) Show ALL the network paths (Points 2) iii) Determine the Critical Path and the total days (Point 3) iv) Determine the float for each activity (Point 5) Dependency Activity Duration Start 0 (days) A 5 (days) B 2 (days) C 3 (days) D 5 days) E 6 (days) F 4 days) G 2 (days) H 5 days) 1 7 (days) 3 (days) Finish 0 (days) Start Start A,B Start Start D, E CAF G G H Q2. From the table shown i) Shown the network diagram and calculate the critical path (Points 6) ii) Project duration (Point 1) Float of task C (Point 1) Early Start of task E (Point 1) Late Finish of Task A (Point 1)