Question: 7-29 General Foundry's project crashing data are shown in Table 7.10 on page 294. Crash this project by hand to 10 weeks. What are the

7-29 General Foundry's project crashing data are shown in Table 7.10 on page 294. Crash this project by hand to 10 weeks. What are the final times for each activity after crashing, and what is the total cost associated with reducing the duration of this project from 15 to 10 weeks?

ACTIVITYTIME(WEEKS)COSTCRAHS COST

STANDARDCRASHSTANDARDCRASHPER WEEK

A21$22,000$22,750$750

B31$30,000$34,000$2000

C21$26,000$27,000$1000

D43$48,000$49,000$1000

E42$56,000$58000$1000

F32$30000$30500$500

G52$80000$84,500$1500

H21$16,000$19,000$3000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!