7-29 General Foundry's project crashing data are shown in Table 7.10 on page 294. Crash this project by hand to 10 weeks. What are the final times for each activity after crashing, and what is the total cost associated with reducing the duration of this project from 15 to 10 weeks?
ACTIVITYTIME(WEEKS)COSTCRAHS COST
STANDARDCRASHSTANDARDCRASHPER WEEK
A21$22,000$22,750$750
B31$30,000$34,000$2000
C21$26,000$27,000$1000
D43$48,000$49,000$1000
E42$56,000$58000$1000
F32$30000$30500$500
G52$80000$84,500$1500
H21$16,000$19,000$3000