Question: 8- As a project manager find out schedule variance with the following values provide, EV =81 and SPI=0.9. A. -7 B. -8 C. -9 D.
8- As a project manager find out schedule variance with the following values provide, EV =81 and SPI=0.9. A. -7 B. -8 C. -9 D. -10 E. Cannot be calculated based on these numbers
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts