Question: 8- As a project manager find out schedule variance with the following values provide, EV =81 and SPI=0.9. A. -7 B. -8 C. -9 D.

 8- As a project manager find out schedule variance with the

8- As a project manager find out schedule variance with the following values provide, EV =81 and SPI=0.9. A. -7 B. -8 C. -9 D. -10 E. Cannot be calculated based on these numbers 9- The project metrics says that the project has for SPI of .83 and CPI of 1.3. How cans the project status BEST described? A. Project is ahead of schedule and under budget B. Project is behind schedule and under budget C. Project is behind schedule and over budget D. Project is ahead of schedule and over budget 10- Project charter is the initial document created. Project charter information includes? A. Project purpose, High level requirements, assumptions and constraints, stakeholder list , summary budget, High level risk. B. Project purpose, Detailed requirements, assumptions and constraints stakeholder list, High level risk. C. Project purpose, assumptions and constraints, project management plan, stakeholder list, summary budget, assumptions and constraints. D. Project purpose, High level requirements, Work Authorization System , assumptions and constraints, assumptions and constraints

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!