Question: As a project manager calculate the schedule variance with the following values provide, EV = 8 1 and SPI = 0 . 9 . Question

As a project manager calculate the schedule variance with the following values provide, EV =81 and SPI =0.9.
Question 15Select one:
a.
-7
b.
-8
c.
Cannot be calculated based on these numbers
d.
-9