Question: 8. In 2017, Dygress Construction Co. began work on a contract for $16,500,000; it was completed in 2018. The following cost data pertain to this

8. In 2017, Dygress Construction Co. began work on a contract for $16,500,000; it was completed in 2018. The following cost data pertain to this contract: Year Ended December 31 2018 Cost incurred during the year Estimated costs to complete at the end of year $5,850,000 $4,200,000 3,900,000 Assuming the performance obligation is satisfied over time, what is the amount of gross profit to be recognized on the income statement for the year ended December 31, 2018? a. $2,400,000 b. $2,695,000 c. $4,050,000 d. $6,450,000 Short Answer Problems: (2 Questions 16 Points each) Question # 1: 8. In 2017, Dygress Construction Co. began work on a contract for $16,500,000; it was completed in 2018. The following cost data pertain to this contract: Year Ended December 31 2018 Cost incurred during the year Estimated costs to complete at the end of year $5,850,000 $4,200,000 3,900,000 Assuming the performance obligation is satisfied over time, what is the amount of gross profit to be recognized on the income statement for the year ended December 31, 2018? a. $2,400,000 b. $2,695,000 c. $4,050,000 d. $6,450,000 Short Answer Problems: (2 Questions 16 Points each) Question # 1
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
