Question: # 8 Problem 1 7 - 1 5 ( Static ) A construction project has indirect costs totaling $ 4 0 , 0 0 0

#8 Problem 17-15(Static)
A construction project has indirect costs totaling $40,000 per week. Major activities in the project and their expected times in weeks are shown in this precedence diagram.
a. Determine the optimum time-cost crashing plan. Continue crashing as long as the total crashing cost at each step is less than or equal to $40.
Week 1:
Week 2:
Week 3:
Week 4:
Week 5:
^^^ It is making me pic an answer for each week from a drop-down menu. The options are each activity (e.g.7-11,1-2,2-5,11-13 & 4-6,7-11 & 6-10). These options also include "Do not crash".
b. Compute total crashing cost and total indirect costs.
Note: Enter numbers in the same format as the crashing cost table, i.e., enter 25 instead of 25,000.
Total crashing costs:
Total indirect costs:
# 8 Problem 1 7 - 1 5 ( Static ) A construction

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!